In an iteration plan, which value is represented by the length of the progress bar

The correct answer is B. The amount of work completed. See the full explanation below for the reasoning.

Question

In an iteration plan, which value is represented by the length of the progress bar

Options

  • AThe amount of work estimated
  • BThe amount of work completed
  • CThe amount of work on schedule
  • DThe amount of active work

How the community answered

(64 responses)
  • A
    5% (3)
  • B
    73% (47)
  • C
    8% (5)
  • D
    14% (9)