A user creates a plan for a project by using the Formal Project Management process template. What is used to define temporal relationships between tasks that are logically related?
The correct answer is D. schedule dependencies. See the full explanation below for the reasoning.
Question
A user creates a plan for a project by using the Formal Project Management process template. What is used to define temporal relationships between tasks that are logically related?
Options
- Aresource leveling
- Bplan attributes
- Cschedule constraints
- Dschedule dependencies
How the community answered
(34 responses)- A3% (1)
- B6% (2)
- C18% (6)
- D74% (25)