C2140-130 · Question #76

Which two statements are true about work performed by project managers and integrators on a UCM project? (Choose two.)

The correct answer is C. Project Managers create UCM projects, establish the policies and monitor project status. D. Integrators build components, create and recommend baselines. See the full explanation below for the reasoning.

Question

Which two statements are true about work performed by project managers and integrators on a UCM project? (Choose two.)

Options

  • AProject Managers create UCM projects and all streams, establish the policies and recommend
  • BIntegrators work on activities, deliver activities and rebase work areas.
  • CProject Managers create UCM projects, establish the policies and monitor project status.
  • DIntegrators build components, create and recommend baselines.

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    17% (5)
  • C
    73% (22)

Community Discussion

No community discussion yet for this question.