IBM
C2140-130 · Question #50
The rebase operation provides the way for developers on a UCM project to update work areas with work that has been integrated, tested, and approved for general use. Which two statements are true…
The correct answer is C. A rebase operation is performed in a view that is attached to the stream that is being rebased. D. An integration activity associated to the rebase operation becomes the current activity of the view. See the full explanation below for the reasoning.
Question
The rebase operation provides the way for developers on a UCM project to update work areas with work that has been integrated, tested, and approved for general use. Which two statements are true about the rebase operation? (Choose two.)
Options
- AThe work areas that are updated can only be development streams.
- BThe developer can perform a rebase operation while a deliver operation is in progress.
- CA rebase operation is performed in a view that is attached to the stream that is being rebased.
- DAn integration activity associated to the rebase operation becomes the current activity of the view
How the community answered
(53 responses)- A15% (8)
- B6% (3)
- C79% (42)
Community Discussion
No community discussion yet for this question.