C2140-130 · Question #38

What are two reasons why project managers lock the Integration Stream? (Choose two.)

The correct answer is A. to build and test a static set of files B. to prevent new files from being delivered. See the full explanation below for the reasoning.

Question

What are two reasons why project managers lock the Integration Stream? (Choose two.)

Options

  • Ato build and test a static set of files
  • Bto prevent new files from being delivered
  • Cto make the stream invisible to developers
  • Dto enable scrubbing

How the community answered

(27 responses)
  • A
    81% (22)
  • C
    11% (3)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.