When a user enters a ClearCase command associated with a preoperation (preop) trigger, the trigger procedure is fired. Which two statements are true? (Choose two.)

The correct answer is A. If the trigger procedure finishes with a failure status, the operation requested by the user is D. If the trigger procedure finishes with a success status, the operation is performed. See the full explanation below for the reasoning.

Question

When a user enters a ClearCase command associated with a preoperation (preop) trigger, the trigger procedure is fired. Which two statements are true? (Choose two.)

Options

  • AIf the trigger procedure finishes with a failure status, the operation requested by the user is
  • BIf the trigger procedure finishes with a failure status, the operation requested by the user is
  • CIf the trigger procedure finishes with a success status, the operation requested by the user is
  • DIf the trigger procedure finishes with a success status, the operation is performed.

How the community answered

(28 responses)
  • A
    75% (21)
  • B
    18% (5)
  • C
    7% (2)