IBM
C2140-130 · Question #3
When a user enters a ClearCase command associated with a preoperation (preop) trigger, the trigger procedure is fired. Which two statements are true? (Choose two.)
The correct answer is A. If the trigger procedure finishes with a failure status, the operation requested by the user is D. If the trigger procedure finishes with a success status, the operation is performed. See the full explanation below for the reasoning.
Question
When a user enters a ClearCase command associated with a preoperation (preop) trigger, the trigger procedure is fired. Which two statements are true? (Choose two.)
Options
- AIf the trigger procedure finishes with a failure status, the operation requested by the user is
- BIf the trigger procedure finishes with a failure status, the operation requested by the user is
- CIf the trigger procedure finishes with a success status, the operation requested by the user is
- DIf the trigger procedure finishes with a success status, the operation is performed.
How the community answered
(28 responses)- A75% (21)
- B18% (5)
- C7% (2)
Community Discussion