What is the proper sequence for running the steps of the program preparation process?

The correct answer is C. Precompile, bind, link edit, compile. prepprocesses.html

Information Analyzer Architecture and Components

Question

What is the proper sequence for running the steps of the program preparation process?

Options

  • APrecompile, compile, link edit, bind
  • BBind, precompile, compile, link edit
  • CPrecompile, bind, link edit, compile
  • DLink edit, precompile, compile, bind

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    77% (24)
  • D
    6% (2)

Explanation

prepprocesses.html

Topics

#program preparation#precompile#bind#link edit