The following warning message is issued when the last available active log data set is 5% full: DSNJ110E - LAST COPY n ACTIVE LOG DATA SET IS nnn PERCENT FULL What will happen if you ignore this…

The correct answer is D. DB2 will automatically allocate more active log data sets as long as there are still less than 93 of. See the full explanation below for the reasoning.

Question

The following warning message is issued when the last available active log data set is 5% full:

DSNJ110E – LAST COPY n ACTIVE LOG DATA SET IS nnn PERCENT FULL What will happen if you ignore this message?

Options

  • ADB2 will shut down if it reaches the 100% full condition
  • BDB2 will overwrite the oldest archive log without archiving
  • CDB2 will stop any activity that requires log writes if it reaches the 100% full condition
  • DDB2 will automatically allocate more active log data sets as long as there are still less than 93 of

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    11% (3)
  • D
    79% (22)