An object (table space, index space or a physical partition of a table space or index space) is in AREST or RESTP status. If backout activity is not already underway, what should occur?
The correct answer is A. Issue a RECOVER POSTPONED command. See the full explanation below for the reasoning.
Question
An object (table space, index space or a physical partition of a table space or index space) is in AREST or RESTP status. If backout activity is not already underway, what should occur?
Options
- AIssue a RECOVER POSTPONED command.
- BIssue a START command with ACCESS(RW).
- CRecycle the system with the system parameter LBACKOUT=NO.
- DIssue a STOP command and then a START command with ACCESS(RW).
How the community answered
(48 responses)- A73% (35)
- B17% (8)
- C4% (2)
- D6% (3)