Objects DB1.TS1 .... DB1.TS10 are in copy pending status. Which of the following actions removes the copy pending state AND creates an entry in SYSIBM.SYSCOPY?

The correct answer is C. Run the COPY TABLESPACE utility with option FULL YES for each of the 10 table spaces. See the full explanation below for the reasoning.

Question

Objects DB1.TS1 .... DB1.TS10 are in copy pending status. Which of the following actions removes the copy pending state AND creates an entry in SYSIBM.SYSCOPY?

Options

  • ARun the BACKUP SYSTEM utility.
  • BRun the REPAIR SET NOCOPYPEND utility.
  • CRun the COPY TABLESPACE utility with option FULL YES for each of the 10 table spaces.
  • DIssue command -START DB(DB1) SP(TSx) ACCESS(FORCE) for each of the 10 table spaces

How the community answered

(57 responses)
  • A
    2% (1)
  • B
    5% (3)
  • C
    84% (48)
  • D
    9% (5)