IBM
C2090-305 · Question #62
You are implementing a rule that evaluates the valid values for an Indicator field. What steps are necessary to tolerate a 1 % error rate in the executed rule?
The correct answer is C. Open Data Rule workspace. See the full explanation below for the reasoning.
Question
You are implementing a rule that evaluates the valid values for an Indicator field. What steps are necessary to tolerate a 1 % error rate in the executed rule?
Options
- AOpen Data Rule workspace;
- BOpen Data Rule workspace;
- COpen Data Rule workspace;
- DOpen Data Rule workspace;
How the community answered
(35 responses)- A3% (1)
- B6% (2)
- C80% (28)
- D11% (4)
Community Discussion
No community discussion yet for this question.