IBM
C2090-304 · Question #20
Which statement is true?
The correct answer is C. To add or remove output links in my QualityStage batch job, you must re-provision the match. See the full explanation below for the reasoning.
Question
Which statement is true?
Options
- AA batch QualityStage match job must have a match statistics output link.
- BYou can override match designer cutoff thresholds within the QualityStage match stage.
- CTo add or remove output links in my QualityStage batch job, you must re-provision the match
- DA comma delimited text file format is required for the match designer sample input data
How the community answered
(47 responses)- A4% (2)
- B9% (4)
- C85% (40)
- D2% (1)
Community Discussion