On the DataStage development server, you have been making enhancements to a copy of a DataStage job running on the production server. You have been asked to document the changes you have made to the…

The correct answer is D. Cross Project Compare. See the full explanation below for the reasoning.

Question

On the DataStage development server, you have been making enhancements to a copy of a DataStage job running on the production server. You have been asked to document the changes you have made to the job. What tool in DataStage Designer would you use?

Options

  • ACompare Against
  • Bdiffapicmdline.exe
  • CDSMakeJobReport
  • DCross Project Compare

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    7% (4)
  • C
    15% (8)
  • D
    75% (41)