When using Deployment Manager, after preparing P8 assets for deployment in the source environment, you need to create which one of the following?

The correct answer is B. A deploy dataset of exported objects. See the full explanation below for the reasoning.

Question

When using Deployment Manager, after preparing P8 assets for deployment in the source environment, you need to create which one of the following?

Options

  • AA set of source object bundles.
  • BA deploy dataset of exported objects.
  • CA set of custom property conversion maps.
  • DAn export manifest of property information in the target system.

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    77% (20)
  • C
    4% (1)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.