Disaster Recovery (DR) planning includes establishing RPO (Recovery Point Objective) and RTO (Recovery Time Objective) values. What is RTO?
The correct answer is D. The RTO is the amount of time that passes from the time a disaster strikes until data center. See the full explanation below for the reasoning.
Question
Disaster Recovery (DR) planning includes establishing RPO (Recovery Point Objective) and RTO (Recovery Time Objective) values. What is RTO?
Options
- AThe RTO is the amount of time it takes to start the DR servers.
- BThe RTO is the amount of time it takes to replicate databases from PRODUCTION to DR
- CThe RTO is the amount of time users are switched to DR site before switching back to
- DThe RTO is the amount of time that passes from the time a disaster strikes until data center
How the community answered
(50 responses)- A8% (4)
- B6% (3)
- C16% (8)
- D70% (35)