C2070-982 · Question #112
What does adding a task to a mutually exclusive task set mean?
The correct answer is D. If you complete one task in the set, you cannot complete any of the other tasks in the set. See the full explanation below for the reasoning.
Question
What does adding a task to a mutually exclusive task set mean?
Options
- AThe task must have a pre-condition
- BThe task must be manually completed
- CAll tasks in that set must be completed
- DIf you complete one task in the set, you cannot complete any of the other tasks in the set
How the community answered
(23 responses)- A4% (1)
- B4% (1)
- C13% (3)
- D78% (18)