C2070-981 · Question #134
The system administrator for a large IBM FileNet Content Manager installation is seeing errors in the P8 error log during high volume times. The error is as follows on an IBM WebSphere Application…
The correct answer is C. Increase the maximum connections for the JDBC connection pool. 01.ibm.com/support/knowledgecenter/SSNW2F_5.1.0/com.ibm.p8.ce.trouble.doc/p8pct018.htm?l
Question
The system administrator for a large IBM FileNet Content Manager installation is seeing errors in the P8 error log during high volume times. The error is as follows on an IBM WebSphere Application Server V7:
Root Exception message:CORBA NO_RESPONSE 0x4942fb01 Maybe; nested exception is:
org.omg.CORBA.NO_RESPONSE: Request 15 timed out vmcid: IBM minor code: B01 completed:
Maybe Connection not available while invoking method createOrWaitForConnection for resource [DATASOURCE_NAME] What can the system administrator do to correct the error?
Options
- AAdjust the Fixed Content Device retention parameters.
- BModify the Content Engine Web Service Transport (CEWS).
- CIncrease the maximum connections for the JDBC connection pool.
- DAdjust the Lightweight Third Party Authentication (LTPA) parameters.
How the community answered
(40 responses)- A3% (1)
- B5% (2)
- C85% (34)
- D8% (3)
Explanation
01.ibm.com/support/knowledgecenter/SSNW2F_5.1.0/com.ibm.p8.ce.trouble.doc/p8pct018.htm?l
Topics
Community Discussion
No community discussion yet for this question.