IBM
C2070-587 · Question #8
C2070-587 Question #8: Real Exam Question with Answer & Explanation
The correct answer is D. Restore the databases and the IBM FileNet Process Engine 3.5 software, then reassign work. See the full explanation below for the reasoning.
Question
A customer is performing a upgrade to IBM FileNet P8 V5.1. They have three environments, DEV (V4.0), Test (V3.5) and PROD (V3.5). After completing the Test system upgrade, the customer is finding many PE work objects in the exception state. Before running the upgrade again, what steps need to be taken in order to correct the issue?
Options
- ARestore the databases and reassign work objects as required.
- BThis is a test system and many users are created by testers, so this is not a problem.
- CRestore the IBM FileNet Process Engine 3.5 software and reassign work objects as required.
- DRestore the databases and the IBM FileNet Process Engine 3.5 software, then reassign work