The Deployment Professional browses through the available actions from the RRunner actions library and notices that the GoToNextFunction action has a red diamond next to it (see below). What does…
The correct answer is C. The GoToNextFunction action will replace the GotoNextRule action. See the full explanation below for the reasoning.
Question
The Deployment Professional browses through the available actions from the RRunner actions library and notices that the GoToNextFunction action has a red diamond next to it (see below). What does this signify?
Exhibit
Options
- AThe GoToNextFunction is a deprecated action
- BThe GotoNextRule action will replace the GoToNextFunction action
- CThe GoToNextFunction action will replace the GotoNextRule action
- DThe GoToNextFunctionEx action will replace the GoToNextFunction action
How the community answered
(15 responses)- A7% (1)
- B13% (2)
- C80% (12)