Question

Disaster Recovery (DR)planning includes establishing RPO (Recovery Point Objective) and RTO (Recovery Time Objective) values. What is RTO?

Options

  • AThe RTO is the amount of time it takes to start the DR servers.
  • BThe RTO is the amount of time it takes to replicate databases from PRODUCTION
  • CThe RTO is the amount of time users are switched to DR site before switching back
  • DThe RTO is the amount of time that passes from the time a disaster strikes until data

Unlock C2070-581 to see the answer