Mary is creating a Program document to run the new Database Maintenance Tool (dbmt) and has specified to run the tool "At server startup only". What command line option(s) must Mary specify in order…
The correct answer is C. -range 2:00AM 5:00AM. See the full explanation below for the reasoning.
Question
Mary is creating a Program document to run the new Database Maintenance Tool (dbmt) and has specified to run the tool "At server startup only". What command line option(s) must Mary specify in order to perform compact operations only between the hours of 2:00 AM and 5:00 AM?
Options
- A-starttime 2:00AM
- B-force 2:00AM 5:00AM
- C-range 2:00AM 5:00AM
- D-timeLimit 2:00AM 5:00AM
How the community answered
(39 responses)- A3% (1)
- B5% (2)
- C82% (32)
- D10% (4)