Which of the following is not a part of Business Understanding phase of the CRISP-DM (Cross industry Standard Process for Data Mining) Methodology?

The correct answer is D. Producing a project Plan. See the full explanation below for the reasoning.

Question

Which of the following is not a part of Business Understanding phase of the CRISP-DM (Cross industry Standard Process for Data Mining) Methodology?

Options

  • ADetermining Business Objectives
  • BDetermining Data Mining Goals
  • CInitial Data Collection
  • DProducing a project Plan

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    16% (6)
  • D
    76% (29)