Which of the following is not a part of Business Understanding phase of the CRISP-DM (Cross industry Standard Process for Data Mining) Methodology?
The correct answer is D. Producing a project Plan. See the full explanation below for the reasoning.
Question
Which of the following is not a part of Business Understanding phase of the CRISP-DM (Cross industry Standard Process for Data Mining) Methodology?
Options
- ADetermining Business Objectives
- BDetermining Data Mining Goals
- CInitial Data Collection
- DProducing a project Plan
How the community answered
(38 responses)- A5% (2)
- B3% (1)
- C16% (6)
- D76% (29)