IBM
C2020-702 · Question #6
You want to load data to Cube A that will result in faster load times while ensuring TM1 can recover the content of the data load in the event of a subsequent server failure. Which technique would…
The correct answer is B. On the T1 Maps/Cube tab. do not select Enable Cube Logging, and add a. See the full explanation below for the reasoning.
Question
You want to load data to Cube A that will result in faster load times while ensuring TM1 can recover the content of the data load in the event of a subsequent server failure. Which technique would you use?
Options
- AOn the T1 Maps/Cube tab, select Enable Cube Logging, and add a CubeSaveData(CubeA)
- BOn the T1 Maps/Cube tab. do not select Enable Cube Logging, and add a
- COn the T1 Maps/Cube tab, select Enable Cube Logging, and add a SaveDataAII function to the
- DOn the T1 Maps/Cube tab, do not select Enable Cube Logging, and add a SaveDataAII function
How the community answered
(45 responses)- A2% (1)
- B80% (36)
- C7% (3)
- D11% (5)
Community Discussion
No community discussion yet for this question.