C2020-701 · Question #32

You are asked to prepare next year's budget for your organization. Because of budgetary pressures for the new year, you are instructed to copy last year's budget into the new year and reduce it by…

The correct answer is C. Relative Proportional Spread followed byPercent Change D. Relative Proportional Spread followed by Relative Percent Adjustment. See the full explanation below for the reasoning.

Question

You are asked to prepare next year's budget for your organization. Because of budgetary pressures for the new year, you are instructed to copy last year's budget into the new year and reduce it by 5%. The TM1 cube you are using contains last year's budgetary data and the new year element has been added. Which two TM1 data spreading operations will allow you to do this? (Choose two.)

Options

  • AProportional Spread followed by Percent Change
  • BRelative Percent Adjustment
  • CRelative Proportional Spread followed byPercent Change
  • DRelative Proportional Spread followed by Relative Percent Adjustment

How the community answered

(56 responses)
  • A
    20% (11)
  • B
    9% (5)
  • C
    71% (40)