Suppose you wanted to select only the records with complete data on all the fields for analysis and need to generate a Select node to perform that operation. Which other node should you use to…

The correct answer is C. Data Audit node. See the full explanation below for the reasoning.

Question

Suppose you wanted to select only the records with complete data on all the fields for analysis and need to generate a Select node to perform that operation. Which other node should you use to generate the Select node?

Options

  • ADerive node
  • BFiller node
  • CData Audit node
  • DFilter node

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    18% (5)
  • C
    71% (20)
  • D
    7% (2)