IBM
C2010-653 · Question #7
The IF/THEN logic of the workflow is failing. Which task should be checked?
The correct answer is C. Switch Task. See the full explanation below for the reasoning.
Question
The IF/THEN logic of the workflow is failing. Which task should be checked?
Options
- AIter Task
- BFork Task
- CSwitch Task
- DCreate Record Task
How the community answered
(32 responses)- A16% (5)
- B6% (2)
- C75% (24)
- D3% (1)
Community Discussion