Question

When a business object (BO) is published, how can one tell that the publish process has been completed?

Options

  • AA pop-up message appears to confirm the BO publication.
  • BThe revised property is not grayed out in the Data Modeler.
  • CAll forms for this BO are automatically published with this BO.
  • DA notification has been sent to the user that triggered the publish process.