An IBM Tivoli Storage Manager (TSM) administrator has been using only the simultaneous write function on the primary storage pool to make offsite copies for disaster recovery. While performing a…

The correct answer is A. Run backup stgpool daily. See the full explanation below for the reasoning.

Question

An IBM Tivoli Storage Manager (TSM) administrator has been using only the simultaneous write function on the primary storage pool to make offsite copies for disaster recovery. While performing a disaster recovery test, the administrator notices that some of the data on the copy storage pool tapes are incomplete and that some data is missing. What should the administrator have also been doing to ensure that a complete set of data was available offsite?

Options

  • ARun backup stgpool daily.
  • BRun prepare drmedia earlier in the day.
  • CRun more than one database backup every day.
  • DRun prepare stgpool every day before tapes go offsite.

How the community answered