In a busy IBM Tivoli Storage Manager V6.3 Server environment some failed backups have gone unnoticed for a few days. The administrator knows that they occurred around 5 days ago at 8:30 in the…

The correct answer is C. q act begind=-5 begint=08:30. See the full explanation below for the reasoning.

Question

In a busy IBM Tivoli Storage Manager V6.3 Server environment some failed backups have gone unnoticed for a few days. The administrator knows that they occurred around 5 days ago at 8:30 in the morning. Which command could the administrator issue to find information about the failed backups?

Options

  • Aq act se=-5 begint=08:30
  • Bq act begint=-5 begind=08:30
  • Cq act begind=-5 begint=08:30
  • Dq log begind=-5 begint=08:30

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    18% (6)
  • C
    73% (24)
  • D
    3% (1)