Which statement is true about scheduling an escalation in IBM Maximo Asset Management V7.5 (Maximo)?

The correct answer is C. Maximo monitors the database when scheduled. See the full explanation below for the reasoning.

Question

Which statement is true about scheduling an escalation in IBM Maximo Asset Management V7.5 (Maximo)?

Options

  • AMaximo performs escalations every hour.
  • BMaximo performs escalations on time intervals.
  • CMaximo monitors the database when scheduled.
  • DMaximo performs the escalation action when scheduled.

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    84% (27)
  • D
    3% (1)