A forecast for a preventive maintenance record has been generated. How can the forecast date be adjusted from the Preventive Maintenance application?

The correct answer is A. From the Forecast tab, select a forecast row, enter a value in the New Date field, click Save. See the full explanation below for the reasoning.

Question

A forecast for a preventive maintenance record has been generated. How can the forecast date be adjusted from the Preventive Maintenance application?

Options

  • AFrom the Forecast tab, select a forecast row, enter a value in the New Date field, click Save
  • BFrom the Select Action menu, select Generate Forecast, enter a value in the Forecast Days field,
  • CFrom the Frequency tab, select the Time Based Frequency tab, enter a value in the Frequency
  • DFrom the Frequency tab, select the Time Based Frequency tab, enter a value in the Extended

How the community answered

(26 responses)
  • A
    73% (19)
  • B
    15% (4)
  • C
    4% (1)
  • D
    8% (2)