IBM
C2010-570 · Question #6
A forecast for a preventive maintenance record has been generated. How can the forecast date be adjusted from the Preventive Maintenance application?
The correct answer is A. From the Forecast tab, select a forecast row, enter a value in the New Date field, click Save. See the full explanation below for the reasoning.
Question
A forecast for a preventive maintenance record has been generated. How can the forecast date be adjusted from the Preventive Maintenance application?
Options
- AFrom the Forecast tab, select a forecast row, enter a value in the New Date field, click Save
- BFrom the Select Action menu, select Generate Forecast, enter a value in the Forecast Days field,
- CFrom the Frequency tab, select the Time Based Frequency tab, enter a value in the Frequency
- DFrom the Frequency tab, select the Time Based Frequency tab, enter a value in the Extended
How the community answered
(26 responses)- A73% (19)
- B15% (4)
- C4% (1)
- D8% (2)
Community Discussion