When creating new Business Intelligence and Reporting Tool (BIRT) reports for use by the various IBM Maximo Asset Management applications, which step correctly describes a part of the process to add…
The correct answer is A. Before design files are imported, any associated library files must be imported. See the full explanation below for the reasoning.
Question
When creating new Business Intelligence and Reporting Tool (BIRT) reports for use by the various IBM Maximo Asset Management applications, which step correctly describes a part of the process to add a new report?
Options
- ABefore design files are imported, any associated library files must be imported
- BUsing the system configuration option, choose the report designer files to import
- CUsing the BIRT Report Designer Workstation, select the menu item to import the new report
- DBefore design files are imported, the location files that specify the location of the images and
How the community answered
(34 responses)- A79% (27)
- B3% (1)
- C12% (4)
- D6% (2)