After fully receiving a shipment, it is discovered that the item or tool is damaged and must be sent back. How is it recorded that the good(s) have been returned in the Shipment Receiving application?
The correct answer is D. Find the shipment receipt, select the button Select Items for Return, select each item and update. See the full explanation below for the reasoning.
Question
After fully receiving a shipment, it is discovered that the item or tool is damaged and must be sent back. How is it recorded that the good(s) have been returned in the Shipment Receiving application?
Options
- AFind the shipment receipt, select New Row, enter the quantity, item, and then select
- BFind the shipment receipt, select New Row, enter the quantity, item, and then select
- CFind the shipment receipt, select the button Select Damaged Items, select each item and update
- DFind the shipment receipt, select the button Select Items for Return, select each item and update
How the community answered
(62 responses)- A3% (2)
- B8% (5)
- C16% (10)
- D73% (45)