In the Work Order Information section of the Preventive Maintenance application which field is mandatory?

The correct answer is D. Work Order Status. See the full explanation below for the reasoning.

Question

In the Work Order Information section of the Preventive Maintenance application which field is mandatory?

Options

  • APriority
  • BLocation
  • CWorkgroup
  • DWork Order Status

How the community answered

(62 responses)
  • A
    15% (9)
  • B
    6% (4)
  • C
    5% (3)
  • D
    74% (46)