Which statement is true regarding the master Preventive Maintenance (PM) record?
The correct answer is D. Associations between existing PM records and a master PM record can be made. See the full explanation below for the reasoning.
Question
Which statement is true regarding the master Preventive Maintenance (PM) record?
Options
- AA master PM record is generated by the Meters application.
- BA master PM record is generated by the Assets application.
- CA master PM record generates work orders like any other PM.
- DAssociations between existing PM records and a master PM record can be made.
How the community answered
(24 responses)- A13% (3)
- B4% (1)
- C4% (1)
- D79% (19)