C2010-570 · Question #2
Which method is used to view labor hours, costs, and material costs for a particular work order?
The correct answer is B. from the Work Order Tracking application, go to the Select Action menu and select View > Costs. See the full explanation below for the reasoning.
Question
Which method is used to view labor hours, costs, and material costs for a particular work order?
Options
- Afrom the Work Order Tracking application, select the Cost tab
- Bfrom the Work Order Tracking application, go to the Select Action menu and select View > Costs
- Cfrom the Actuals tab of Work Order Tracking application, download and summarize each of the
- Dnavigate to the Cost Management application, query for the work order in question to view
How the community answered
(43 responses)- A16% (7)
- B72% (31)
- C5% (2)
- D7% (3)