C2010-570 · Question #2

Which method is used to view labor hours, costs, and material costs for a particular work order?

The correct answer is B. from the Work Order Tracking application, go to the Select Action menu and select View > Costs. See the full explanation below for the reasoning.

Question

Which method is used to view labor hours, costs, and material costs for a particular work order?

Options

  • Afrom the Work Order Tracking application, select the Cost tab
  • Bfrom the Work Order Tracking application, go to the Select Action menu and select View > Costs
  • Cfrom the Actuals tab of Work Order Tracking application, download and summarize each of the
  • Dnavigate to the Cost Management application, query for the work order in question to view

How the community answered

(43 responses)
  • A
    16% (7)
  • B
    72% (31)
  • C
    5% (2)
  • D
    7% (3)