What is required to create an escalation?

The correct answer is B. Schedule. See the full explanation below for the reasoning.

Question

What is required to create an escalation?

Options

  • ASite
  • BSchedule
  • CCondition
  • DDescription

How the community answered

(30 responses)
  • A
    13% (4)
  • B
    77% (23)
  • C
    3% (1)
  • D
    7% (2)