What does the Enable Repair Facilities Organization option allow?

The correct answer is A. Creating a work order in a site different from the site of the asset on that work order. See the full explanation below for the reasoning.

Question

What does the Enable Repair Facilities Organization option allow?

Options

  • ACreating a work order in a site different from the site of the asset on that work order
  • BReserving items from one site to use at another site on an emergency maintenance work order
  • CMoving an asset from one location to another location on an emergency maintenance work order
  • DCreating a preventive maintenance (PM) record in a site different from the site of the asset on that

How the community answered

(43 responses)
  • A
    77% (33)
  • B
    5% (2)
  • C
    14% (6)
  • D
    5% (2)

Community Discussion

No community discussion yet for this question.