nerdexam
IBM

C2010-570 · Question #142

Preventive Maintenance (PM) work orders can be triggered by which two criteria? (Choose two.)

The correct answer is A. Meter-based PMs based on asset meter readings B. Time-based PMs based on elapsed time since previous work. See the full explanation below for the reasoning.

Question

Preventive Maintenance (PM) work orders can be triggered by which two criteria? (Choose two.)

Options

  • AMeter-based PMs based on asset meter readings
  • BTime-based PMs based on elapsed time since previous work
  • CUnit measure-based PMs based on the threshold of the Unit of Measure application
  • DAsset-based PMs based on the status of the asset when it is moved in the maintenance
  • EItem Master-based PMs based on the status of the item when it is moved in the maintenance

How the community answered

(30 responses)
  • A
    70% (21)
  • C
    20% (6)
  • D
    7% (2)
  • E
    3% (1)

Community Discussion

No community discussion yet for this question.

Full C2010-570 Practice