IBM
C2010-570 · Question #142
Preventive Maintenance (PM) work orders can be triggered by which two criteria? (Choose two.)
The correct answer is A. Meter-based PMs based on asset meter readings B. Time-based PMs based on elapsed time since previous work. See the full explanation below for the reasoning.
Question
Preventive Maintenance (PM) work orders can be triggered by which two criteria? (Choose two.)
Options
- AMeter-based PMs based on asset meter readings
- BTime-based PMs based on elapsed time since previous work
- CUnit measure-based PMs based on the threshold of the Unit of Measure application
- DAsset-based PMs based on the status of the asset when it is moved in the maintenance
- EItem Master-based PMs based on the status of the item when it is moved in the maintenance
How the community answered
(30 responses)- A70% (21)
- C20% (6)
- D7% (2)
- E3% (1)
Community Discussion
No community discussion yet for this question.