IBM
C2010-570 · Question #122
Which statement is true regarding the View Costs table as displayed from the Work Order Tracing application?
The correct answer is A. The Work Package Totals table shows the cost information for the entire work order hierarchy. See the full explanation below for the reasoning.
Question
Which statement is true regarding the View Costs table as displayed from the Work Order Tracing application?
Options
- AThe Work Package Totals table shows the cost information for the entire work order hierarchy
- BAll actual labor hours are immediately reflected in the View Costs table regardless of the work
- CService costs include all services acquired on purchase orders that are charged to the work order
- DThe data reflected in the Estimate at Approval column reflects the work order costs when first
How the community answered
(46 responses)- A83% (38)
- B4% (2)
- C11% (5)
- D2% (1)
Community Discussion
No community discussion yet for this question.