C2010-570 · Question #11
A reservation is created when a work order is approved with item(s) on the Work Order Plans Materials sub-tab. Which action controls when an item must be specified with a hard reservation?
The correct answer is D. Set the flag on this check box within the Inventory application: Requires hard reservation on use? See the full explanation below for the reasoning.
Question
A reservation is created when a work order is approved with item(s) on the Work Order Plans Materials sub-tab. Which action controls when an item must be specified with a hard reservation?
Options
- AChange the reservation type on the materials line to HARD
- BChange the reservation type on the reservation list to HARD
- CSet the reservation type to HARD within the Organization > Inventory Options
- DSet the flag on this check box within the Inventory application: Requires hard reservation on use?
How the community answered
(26 responses)- A4% (1)
- B12% (3)
- C4% (1)
- D81% (21)