Which statement is true regarding job plan editing?
The correct answer is B. To make a change to an in-use job plan (status = ACTIVE) use the select action command to. See the full explanation below for the reasoning.
Question
Which statement is true regarding job plan editing?
Options
- AAn active job plan can be edited after changing its status to DRAFT.
- BTo make a change to an in-use job plan (status = ACTIVE) use the select action command to
- CWith a job plan in the ACTIVE status, only the job plan description and responsibility sections can
- DTo share a job plan with another site or organization, use the Duplicate Job Plan function from the
How the community answered
(48 responses)- A4% (2)
- B77% (37)
- C6% (3)
- D13% (6)