IBM
C2010-570 · Question #103
A work order has three hours of labor charged but only one hour is reflected in the View Costs table. What is a valid explanation for this?
The correct answer is A. Only one hour is an approved labor transaction. See the full explanation below for the reasoning.
Question
A work order has three hours of labor charged but only one hour is reflected in the View Costs table. What is a valid explanation for this?
Options
- AOnly one hour is an approved labor transaction
- BOutside labor hours are not reflected in the View Costs table
- CTwo of the hours were worked by an outside contractor so those hours are reflected as a Service
- DThe view actuals date filter is set for 30 days and two of the hours were recorded greater than 30
How the community answered
(42 responses)- A83% (35)
- B10% (4)
- C5% (2)
- D2% (1)
Community Discussion
No community discussion yet for this question.