A master PM can be used to do which of the following?

The correct answer is C. Create associated PMs for an item's location. See the full explanation below for the reasoning.

Question

A master PM can be used to do which of the following?

Options

  • ACreate a job plan revision.
  • BGenerate work orders for associated PMs.
  • CCreate associated PMs for an item's location.
  • DChange the status of work orders generated from associated PMs.

How the community answered

(20 responses)
  • A
    5% (1)
  • C
    85% (17)
  • D
    10% (2)