A vendor requires a payment of 20% of the purchase price when the purchase order (PO) is sent and the company wants to withhold of the payment until 90 days after receiving the item before final…
The correct answer is D. A Purchase Contract would be created with a payment schedule with an invoice of 20% at the time. See the full explanation below for the reasoning.
Question
A vendor requires a payment of 20% of the purchase price when the purchase order (PO) is sent and the company wants to withhold of the payment until 90 days after receiving the item before final payment is made. How would this be accomplished?
Options
- AA Purchase Requisition would be created and three invoices would be generated via the invoicing
- BA Price Contract would be created with a payment schedule with an invoice of 20% at the time the
- CA Blanket Contract would be created with a payment schedule with an invoice of 20% at the time
- DA Purchase Contract would be created with a payment schedule with an invoice of 20% at the time
How the community answered
(35 responses)- A3% (1)
- B9% (3)
- C17% (6)
- D71% (25)