The job plan coordinator needs to add new tasks to an existing job plan which is currently revision 2. The coordinator selects Revise Job Plan from the More Actions menu and now has a new job plan…
The correct answer is A. ACTIVE. See the full explanation below for the reasoning.
Question
The job plan coordinator needs to add new tasks to an existing job plan which is currently revision 2. The coordinator selects Revise Job Plan from the More Actions menu and now has a new job plan version, revision 3. What is the status of revision 2?
Options
- AACTIVE
- BPNDREV
- CREVISED
- DINACTIVE
How the community answered
(43 responses)- A74% (32)
- B9% (4)
- C14% (6)
- D2% (1)