A company wants the escalation action and notification to be applied to an expired purchase contract. Which of the following must be defined?
The correct answer is C. Escalation Point. a181d6155e3a/entry/maximo_sccd_escalations_your_friend_and_mine1?lang=en
Administration and Operations
Question
A company wants the escalation action and notification to be applied to an expired purchase contract. Which of the following must be defined?
Options
- ASite
- BOrganization
- CEscalation Point
- DEscalation Group
How the community answered
(16 responses)- A6% (1)
- B13% (2)
- C75% (12)
- D6% (1)
Explanation
a181d6155e3a/entry/maximo_sccd_escalations_your_friend_and_mine1?lang=en