nerdexam
IBM

C2010-555 · Question #27

A company wants the escalation action and notification to be applied to an expired purchase contract. Which of the following must be defined?

The correct answer is C. Escalation Point. a181d6155e3a/entry/maximo_sccd_escalations_your_friend_and_mine1?lang=en

Administration and Operations

Question

A company wants the escalation action and notification to be applied to an expired purchase contract. Which of the following must be defined?

Options

  • ASite
  • BOrganization
  • CEscalation Point
  • DEscalation Group

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    13% (2)
  • C
    75% (12)
  • D
    6% (1)

Explanation

a181d6155e3a/entry/maximo_sccd_escalations_your_friend_and_mine1?lang=en

Topics

#escalation point#purchase contracts#contract expiry notification#escalation configuration

Community Discussion

No community discussion yet for this question.

Full C2010-555 Practice