A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks grouped with a new parent work order. Which option will group…
The correct answer is A. Select the task work orders and Create Work Package. See the full explanation below for the reasoning.
Question
A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks grouped with a new parent work order. Which option will group the tasks?
Options
- ASelect the task work orders and Create Work Package.
- BSelect the task work orders Create Job Plan from Work Plan.
- CCreate a new work order and add the task work orders on the Plans tab.
- DCreate a new work order and add the child work orders on the Plans tab.
How the community answered
(58 responses)- A72% (42)
- B9% (5)
- C14% (8)
- D5% (3)