A company wishes to configure Maximo so that meter readings automatically create work orders based on condition monitoring points. The company has already configured the system in Organizational…

The correct answer is B. A continuous type meter should be added to an asset and the PMWOGenCronTask should be. See the full explanation below for the reasoning.

Question

A company wishes to configure Maximo so that meter readings automatically create work orders based on condition monitoring points. The company has already configured the system in Organizational settings and created the appropriate condition monitoring points. What additionally needs to be configured for this be accomplish?

Options

  • AAny meter should be added to the asset and the ConditionMonWoGenCronTask should be active
  • BA continuous type meter should be added to an asset and the PMWOGenCronTask should be
  • CA gauge type meter should be added to an asset and the MeasurePointWoGenCronTask should
  • DA characteristic type meter should be added to an asset and the ConditionMonWoGenCronTask

How the community answered

(52 responses)
  • A
    4% (2)
  • B
    79% (41)
  • C
    12% (6)
  • D
    6% (3)

Community Discussion

No community discussion yet for this question.

Full C2010-555 Practice