Cutover work from cooling to heating is performed on the air handling units during the month of October each year. A requirement is to have the PM record generate Work Orders every Sunday during…
The correct answer is B. Frequency = 7, Frequency Units = DAYS, and Active Days and Dates values entered on the. See the full explanation below for the reasoning.
Question
Cutover work from cooling to heating is performed on the air handling units during the month of October each year. A requirement is to have the PM record generate Work Orders every Sunday during October. What settings are necessary?
Options
- AFrequency = 1, Frequency Units = MONTHS, and Active Dates values entered on the Seasonal
- BFrequency = 7, Frequency Units = DAYS, and Active Days and Dates values entered on the
- CFrequency = 7, Frequency Units = DAYS, and Generate Work Order When Meter Frequency is
- DFrequency = 1, Frequency Units = WEEKS, and Use Last Work Order's Start Date to Calculate
How the community answered
(21 responses)- A5% (1)
- B76% (16)
- C14% (3)
- D5% (1)